TUCC vault addition
New Linear Accelerator Vault addition to an existing health care facility. Scope included new electrical equipment, branch wiring, new lighting, turnkey fire alarm and raceways/connections to the new linear accelerator machine. Project took a lot of coordination with the existing facility staff and medical equipment providers to be completed in nine months.
Owner | Charter Realty Group
Architect | Boulder Associates, Inc.
Engineer | Cator Ruma & Associates
General contractor | GE Johnson Construction Company
Contract value | $235,322